Technology Center

Repair method of rotor stator of flotation machine

Writer: admin Time:2020-10-20 11:24 Browse:

  The rotor and stator of the flotation machine is an indispensable part of the flotation machine. What should be done if the rotor and stator fails? The flotation machine rotor and stator manufacturer will tell you how to repair the flotation machine rotor and stator. I hope it will help you.
  repair material: RJ-C-14-16 wear-resistant material:
  1. Surface treatment: repair welding, degreasing treatment, sandblasting and rust removal for the workpiece to be treated.
  ① Repair welding: repair welding is required for parts that are excessively eroded and not enough to support the strength of the adhesive.
  ②Degreasing and dehumidification treatment: remove the grease on the surface of the workpiece, wipe the surface of the workpiece with cotton yarn, and the cotton yarn has no oil stains or water stains. Adjust the flame to 10CM length with oxygen acetylene, and make the flame to bake the surface of the workpiece repeatedly and evenly at a speed of 5cm/min to remove the grease and moisture on the surface of the workpiece.
Repair method of rotor stator of flotation machine.
  ③Sand blasting and rust removal: remove the oxide layer on the surface of the workpiece and visually inspect it. The sandblasted surface can see a uniform metal color. The workpiece after sandblasting is not allowed to directly touch the sandblasted surface with greased gloves. After sandblasting, the workpiece should be protected from moisture.
  2. Gluing: prepare the mold and tools, preheat the workpiece, preheat the adhesive, and mix and stir in strict accordance with the ratio of the adhesive. After the mixing is completed, the adhesive is placed in the material tray to apply the glue to the preheated workpiece, after mixing The adhesive stays in the tray for no more than 3 minutes to ensure that the adhesive fully adheres to the workpiece. After the construction is completed, timely repair the defects detected.
  3, curing: natural curing for 24 hours at room temperature 30°, different conditions can extend the curing time.
  4. Grinding: The workpiece after heating and solidification shall be ground in strict accordance with the size of the workpiece, and the matching surface shall be sealed and tested.
  5. Paint spray: After passing the inspection, spray paint on the workpiece. The spray paint surface is required to be uniform and no sagging is allowed.
  I believe that through the introduction of Chaishang Trading Co., Ltd., you have already understood the repair of the rotor and stator of the flotation machine. For more information about the rotor and stator, please refer to other content on this site, or call for detailed inquiries.

CATEGORIES

CONTACT US

Company: Dezhou Chaishang Shangmao Co.,Ltd.

Contact: Jack Ma

Fax: 86-534-2798881

Phone: 86-15621266667

Email: Jackma@dzchaishang.com

Add: Room1016, Donghui Building ,Dezhou City , Shandong Province , China.

Scan the qr codeClose
the qr code